What is accomplished during the definition phase of the Rummler-Brache approach?

Study for the Six Sigma White Belt Test. Prepare with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

During the definition phase of the Rummler-Brache approach, the primary focus is on defining project goals and scopes. This phase is essential because it establishes a clear understanding of what the project aims to achieve and sets the boundaries within which the project will operate. By defining the goals, the team can align their efforts, resources, and strategies towards achieving specific outcomes that meet stakeholder expectations.

This phase includes identifying the problem or opportunity to be addressed and articulating the purpose of the project. Having clearly defined goals helps ensure that everyone involved understands the objectives and can work cohesively towards them, ultimately contributing to the project's success. By establishing these parameters early on, the team reduces the risk of scope creep and maintains focus throughout the project.

Other aspects, such as implementation of changes, setting performance metrics, or conducting employee training, occur in later phases of the project where the groundwork laid in the definition phase is built upon to execute the plan effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy