In the context of Scrum, what is the goal of having smaller phases of development known as sprints?

Study for the Six Sigma White Belt Test. Prepare with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

The goal of having smaller phases of development known as sprints in Scrum is to simplify development by concentrating on specific aspects of a project one at a time. By breaking the overall development process into manageable segments, teams can work on a defined set of tasks during each sprint. This approach enables teams to focus on delivering a potentially shippable product increment at the end of each sprint, allowing for greater clarity and direction.

Moreover, sprints promote adaptability; teams can respond more quickly to feedback and changing requirements since they regularly review and adjust their work. This iterative process helps in managing complexity, ensuring that each part of the project receives adequate attention and can be thoroughly developed and tested before moving on to the next phase. It also enhances collaboration and communication among team members, contributing to the overall effectiveness of the development process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy